

Over the past ten years or working with concrete customers, I have seen at least three different ways to calculate rebar overlap length for splicing, and I wanted to share them with you, get your opinions and possibly learn some new ways.
Which do you like or dislike? let me know as I think we all could learn something new from the talent pool of amazing users at zzTakeoff.
Also let us know if you have a different way that you would like to share.
Method one- Common denominator x rebar diameter
The specifications will sometimes require a multiplier between 30 and 50 times the diameter of the rebar for overlap splicing.
a). 40 times .67 for #4 rebar would give you 26” to overlap for splicing
b). 40 times .875 for #7 rebar would give you 35” to overlap for splicing
So basically, this is easy to use in a formula in zzTakeoff, if your rebar list has the diameter in the product list as well as the weight per foot.
Method two- Standard Length
There is no denominator or factor, just overlap 24-36” as needed.
a). #4 rebar the splice would be to use a 24”
b). #7 rebar the splice would be to use a 36”
So the math is easier to understand in zzTakeoff, and if you put the splice length in your rebar product list it becomes very versatile. I suspect that this formula may not meet some of the more difficult specifications that you could see in structural concrete.
Method three- Common denominator by rebar number
I learned this one last week from a very successful structural concrete contractor, and I really like it and it basically multiples .625 times the rebar number, not by the rebar diameter
a). #4 rebar the splice would be 4 x .625 and the splice would be 2.5 feet
b). #7 rebar the splice would be 7 x .625 and the splice would be 4.375 feet
As a side note, I am curious if our rebar users, deduct the splice from the length of the rebar, then calculate the total length of rebar by the new length?
See below:
Let’s say I have a 200 foot linear run of rebar that needs only one strand of #4 and we are using 20’ lengths.
a). would you just find out the total number of 20’ rebar (10 in this case) then multiply that times the rebar overlap (will use 2’) and get 220 feet of rebar.
b). would you deduct the 2 foot rebar splice from the 20’ and then divide the total length needed by 18 feet, which gives you 11.11 pieces of rebar or 222.22 feet?
I have always calculate the above a). method and the Rebar times diameter times a factor, but the math can really get messy in the formula section. I kind of like the B method as well.
Your thoughts are very welcome on this as we have so many talented users in zzTakeoff and I think the responses here would really help our community.
We use method one and method two depending on how the plans are detailed and specified. Some engineers specify lap length in inches and some specify it in X bar diameters. I've never used method 3 which really just looks like bar diameters with the /8 of 4/8 rebar pulled out and put in a decimal number that doesn't line up with what we typically see engineers specify.
Regarding how we estimate it, if it's a 20' stick with 2' lap, we add 10% to our waste number. If it's verticals in a masonry wall with #5's, a 56" lift height, and a 30 bar diameter lap, we add lift height of 56" plus lap of 18 3/4" to make the dowels 74 3/4" plus a couple inches for room for error. If it's a difficult rebar package, we get rough quantities to use for verification and send it out to Blue Rebar to do their own takeoffs, shop drawings, and fabrication. Those guys are the pros when it comes to rebar and I believe they are using zz now too.