Hey fam -
Looking for best practice recommendations to handle the call outs in a plan (see screenshot below).
Once the pipe segments are measured and the fittings are counted, I'd like to also count and "mark off" the callouts.
I was thinking an opaque highlighting of the callout or something could mark them off, but what would be really valuable would be to have a separate type of count, like a faux count, that I could compare to the fittings marked on the plan to ensure that everything was captured.
So if I had sixteen 90 fittings in my count and had sixteen 90 callouts in my count (that would not appear in the export) that would be nice for a double check.
In the meantime, does anyone have a surefire way of marking these callouts off so visually they seem "done"?
Best!

Hi, you could use another count takeoff, change the icon to a checkmark, and make it green. This would work to give you a total and a visual indicator of completion.