Is overlay possible for updated plans, when old set of plans and takeoffs were done in another software(PlanSwift)?

I work for a GC and we build large multifamily projects. We have switched to zz and don't plan on leaving this great software. It would save me a ton of time if I could somehow overlay all takeoffs with updated plans since we switched software. I hope you can help, and thanks for all you do!

Shawn M 2h 42m

Hello David & Welcome to ZZ! ZZ rocks like ZZ Top🤘!


If you import the project from the software that shall not be named, it will pull it in as a ZZ Project. You will then have the ability to load in the new plans and overlay them.


Note: if you have any type of assemblies that were built in PS, they won't translate too well in ZZ. Still worth a try to bring a project in though.


Do you need any help importing the PS projects?