Parents, children, siblings, etc

So, going back to this thread I wanted to see if the sibling/sibling could somehow accumulate/rollup/sum qty's from siblings or if I should approach strategy differently?

I know that I can always throw sub/lab cost type under mat or vice-versa but I really would prefer to have all cost type resources on same level.

This may go back to the conversation I saw a few weeks ago about assemblies capturing MLESO cost types...



Anyway, just thought I'd throw the question out and see what came out - TIA

0

Can you throw a screen shot of the takeoff right pane and some of the formulas you used so I can noodle on this more.

Screenshot of one of the SS assemblies with material item/part


The subcontract item/part is empty because I gave up trying...



@Kyle


OK, I took another look and I think I got it now

Probably going to approach differently now, but at least I got the concepts down I was looking for of traversing up/down parent/child. Learning usage was a fun one to wrap my head around this AM!

I appreciate you inspiring me to use the "Other" cost type as an assembly placeholder from another post.



@Chaz,


Wow Cool! I've been wondering how to make steel takeoffs better without so many freaking conditions. Great idea to use "Usage" for another sort. I have had myself thinking how to make the "usage" field more useful, for example if we had a company standard list we could make that a dropdown for one thought.