Production Rate- Crew Hrs

Hello All,

Here is an idea and way to calculate "crew hrs" using an "Item". I use this to figure out a crew hour rate to install a certain size pipe, at an average depth, between two points. (manhole to manhole in my case). I have made Production rate variables so it can easily be changed depending on the size and type of pipe. Hope this is helpful to someone.


Thanks for sharing Bryan! This is awesome 🙂